Rammed Earth construction uses forms similar to poured-in-place concrete.
At CNBW, the Rammed Earth project was one of four columns which will eventually
support a roof above an outdoor oven.
|
|
The soil mix is poured into the form in lift no more than 8 inches deep.
Before more dirt can be added, the lift is compacted down to 5 inches.
|
|
After the Rammed Earth has cured overnight, Keith Lindauer removes the forms.
|
|
The finished column. Near the bottom you can see layers of different colors.
This was done intentionally to give the column a geological look. Because we
rushed the pounding and didn't get into the corners real good, there is a
little bit of sluffing at the edges.
|